Removal Of Foreign Material:
Overtime Balconies and concrete in general gets covered with decretive material, tile, carpet, stains and paint. All this needs to be removed. With this the process begins. grinding off the old material and then pressure cleaning the surface to the original poured concrete.
Excavation of Damaged Material:
The excavation process starts with cutting the concrete along the marks made by the engineer. Once the area has been cut we chip out the damaged material. The cutting process protects the surrounding areas from damage by the chipping.
Engineering The Excavation:
The excavated area is reviewed for hidden damage within the concrete. The reebar is inspected for rust and damage. The Reebar is cleaned and repaired or replaced , and covered with a protective coating of rust resistant material.